Fig. 7: Shotcrete equipment setup Fig. 8: Shotcrete crew cutting and doing the rough finish using mechanical trowel Fig. 9: Finished section of reservoir (basin) wall The Outstanding Infrastructure Project Project Name McCormick Dam & Power Station: Submerged Concrete Repairs Project Location Baie-Comeau, QC, Canada Shotcrete Contractor Béton projeté MAH Inc. General Contractor BBMarine Architect/Engineer Groupe-conseil TDA Material Supplier/Manufacturer King Shotcrete Solutions* Project Owner Société en Commandite Hydroélectrique Manicouagan *Corporate Member of the American Shotcrete Association Fig. 10: Finished section Shotcrete • Winter 2015 39